- Installation, commissioning, and usage instructions for cool[ 2025-06-10 ]
- 1. The direction of the inlet and outlet pipes of a small counter current tower can be arbitrarily selected in a horizontal position, but it must not collide with the foundation. If there is a foundation in the middle, its load should be 25% of the operating weight, and the remaining 75% should be evenly borne by the peripheral rectangular foundation. If installed on the roof, the additional pressure caused by the load should be considered. 2. A bracket should be installed at the connection between the cooling tower and the inlet and outlet pipes to prevent excessi