1. The direction of the inlet and outlet pipes of a small counter current tower can be arbitrarily selected in a horizontal position, but it must not collide with the foundation.
If there is a foundation in the middle, its load should be 25% of the operating weight, and the remaining 75% should be evenly borne by the peripheral rectangular foundation. If installed on the roof, the additional pressure caused by the load should be considered.
2. A bracket should be installed at the connection between the cooling tower and the inlet and outlet pipes to prevent excessive weight from pressing on the tower wall.
3. The fan blades should be adjusted before installation and use to maintain consistent angles. The method is to mark the front and rear edges of each blade at a distance of 150 millimeters near the inter leaf space, and then measure the distance between the front and rear edges of each blade using the lower chord of the support to calculate the height difference between the front and rear edges of each blade. By adjusting the height difference several times to achieve consistency, it is considered qualified.
4. After connecting the motor, the junction box should be sealed, and attention should be paid to ensuring that the current test value does not exceed the motor's rated current.
5. When starting the cooling tower, be sure to start the water pump first and then turn on the fan. It is not allowed to operate the fan without pouring water. The fan can be turned in reverse at low speed for a short period of time to remove ice.
6. The reducer should be lubricated with 50 # anti-wear gear oil or engine oil before use. The oil should be replaced after 100-300 hours of initial operation and every 3000-5000 hours thereafter. The oil level should be moderate, and the oil gauge should be easy to observe.
7. When the cooling tower is in operation, there should be a dedicated person to manage it, regularly pay attention to changes in current and water temperature, and regularly inspect the motor, reducer, water distributor, and other parts